Desain Jalan Tambang PT. Vale Indonesia Tbk Sorowako

Authors

  • Habibie Anwar
  • Alam Budiman Thamsi Universitas Muslim Indonesia

DOI:

https://doi.org/10.58227/jmi.v2i1.263

Keywords:

Design, Road Geometry, Cross Slope, Road Mine

Abstract

The main function of the mine road is to support the smooth of mining operation, especially in transportation activities, so the good mine road is necessary to design to improve hauling productivity. This research aimed to determine the ideal road geometry for the transportation activities. The data used in this research are topography map, transportation equipment specification data, SOP (standard operational procedure) of road design, and road geometry data. Data processing is conducted to make the calculation of road geometry using rational formula, then based on the result of the calculation, the design of mining road is made. The results of the research showed that the minimum road widths for the straight road are 22 m and for the bend are 28 m, then have the grade of 10% or 3.6°, have the cross slope with height of 3%, and for the bend with width 28 m. The good superelevation used is 6% m. In conclusion, the geometry of mine road at PT. Vale Indonesia, Tbk has been the ideal for fulfilling the hauling activities.

References

Herdiansyah, S., & Zaenal, I. (2022, August). Kajian Teknis Geometri Jalan Tambang untuk Mengurangi Dampak Slippery sebagai Upaya Meningkatkan Produksi Nikel PT ANTAM (Persero) Tbk di Kecamatan Maba, Kabupaten Halmahera Timur, Provinsi Maluku Utara. In Bandung Conference Series: Mining Engineering (Vol. 2, No. 2, pp. 441-447).

Ikhsan, M., & Yatjong, I. (2024). Rancangan Desain Tambang Nikel Laterit Pada Blok D PT. Pernick Sultra Site Waturambaha Kecamatan Lasolo Kepulauan Kabupaten Konawe Utara Provinsi Sulawesi Tenggara. Mining Science And Technology Journal, 3(2), 64-70.

Jamaluddin, F. (2023). Perancangan Geometri Jalan Tambang Pada Pit 3E PT. Aneka Nusantara Internasional. Indonesian Mining Professionals Journal, 5(1), 21-28.

Mili, M. Z., & Anshari, E. (2023). Rancangan Teknis Penambangan Dan Penjadwalan Produksi Jangka Pendek (Short Term Scheduling) Pada Penambangan Bijih Nikel Laterit Pada Pit A Blok Itb Pt Bosowa Mining Site Wawoheo Kecamatan Wiwirano Kabupaten Konawe Utara Provinsi Sulawesi Tenggara. Jurnal Riset Teknologi Pertambangan, 3(2), 40-50.

Mubarak, Z., Aditya, E., & Ir Barlian Dwinagara, M. T. (2019). Perubahan Standar Desain Jalan Tambang Boboka Site Tanjung Buli Berdasarkan Kajian Geoteknik Untuk Mengurangi Material Movement Dan Mempercepat Development Jalan Tambang. Prosiding Temu Profesi Tahunan PERHAPI, 1(1), 553-560.

Nori, S. D. C. (2023). Perencanaan teknis desain jalan tambang pada PIT C sequence 1 Blok Keuno PT. Djava Berkah Mineral jobsite PT. Bumanik Desa Keuno, kecamatan Petasia Timur, kabupaten Morowali Utara, provinsi Sulawesi Tengah (Doctoral dissertation, Institut Teknologi Nasional Yogyakarta).

Rochim, N., Triantoro, A., & Hakim, R. N. (2021). Evaluasi Kondisi Jalan Tambang Berdasarkan Geometri Untuk Meningkatkan Produktifitas Alat Angkut Pada PT Madhani Talatah Nusantara. Jurnal Himasapta, 6(1), 27-32.

Wibawa, N. A., Anshari, E., Saputra, I., & Ambarsari, I. S. (2024). Rancangan Pit Dan Sequence Penambangan Bijih Nikel Pada Pit B Blok Mangrove Pt. Indrabakti Mustika Site Lameruru. Jurnal Riset Teknologi Pertambangan, 4(1), 1-13.

Wita, R., & Wijaksana, I. K. (2024). Kajian Desain Jalan Tambang Pengangkutan Batubara dari Pit Menuju Stockpile. Jurnal Riset Teknik Pertambangan, 9-20.

Yulanda, Y. A., Wiratama, J., Harahap, A. R., & Yudanto, V. S. Y. (2023). Upaya Pengurangan Durasi Slippery Jalan Angkut Overburden dan Rekomendasi Desain Geometri Jalan di PT. Bintang Sukses Energi: Efforts to Reduce the SLippery Duration of Overburden Transport Road and Recommendations for Road Geometry Design at PT. Bintang Sukses Energi. JTK (Jurnal Teknik Kebumian), 10(01), 1-10.

Downloads

Published

2024-01-30

How to Cite

Anwar, H., & Thamsi, A. B. (2024). Desain Jalan Tambang PT. Vale Indonesia Tbk Sorowako. Journal of Mining Insight, 2(1), 14–18. https://doi.org/10.58227/jmi.v2i1.263