Perencanaan Kebutuhan Pompa Untuk Sistem Dewatering Tambang Emas Desa Bakan Kabupaten Bolaang Mongondow

Authors

  • Annisya Putri Hamdan Universitas Muslim Indonesia
  • Anshariah Anshariah Universitas Muslim Indonesia
  • Hasbi Bakri Universitas Muslim Indonesia
  • Firman Nullah Yusuf Universitas Muslim Indonesia

DOI:

https://doi.org/10.58227/jmi.v1i1.40

Keywords:

Mine Dewatering, catchment area, pit, runoff discharge, Multiflo MFC 385 pump

Abstract

One of the most frequent problems in open pit mining methods is the presence of water puddles in the lowest elevation of the pit. This often causesthe delay of production activities.Therefore, it is a need to design a good drainage system planning to deal with it. In this regard, pumps were needed. The aim of this research was to determine the of needed pumps and the best type of pumps to remove water in the pit effectively. This research used maps of mining sequence planningwhich would be then analysed with software Surpac 6.5.1.This was to identifythe width of catchment area. Furthermore, the rainfall data wasanalysed using polygon Thiessen method. The next process is to determine the rainfall plan with Gumbel method. Next was to determine the rainfall intensity plan by using Mononobe equations. Following this was determine the total discharge using rational method. Finally, the process was ended with the determining of the pumps type and pumps spesification to dry the water puddles in the pit. the result indicated that in the sump of the 3rd quarter 2020 with 100 l / sec pumping flow, pumping time 14 hours, total head 76.26 m, recommended pump type is a Multiflo MFC 385 with a rotation speed of recommendation per minute of 1400-1500, and an efficiency of 60% -65%. For 4th quarter sump 2020 with 105l / sec pumping discharge, 20 hour pumping time, total head 105,91 m, recommended type of pump is Multiflo MFC 385 with rotation speed recommendation permenit 1600-1700, with efficiency 60%. For the 1st quarter sump 2021 with a pumping rate of 102 l/sec, the pumping time is 20 hours, total head is 122.26 m, the recommended type of pump is Multiflo MFC 385 with a rotation speed of recommendation per minute 1700-1800, with 50% -60% efficiency. It can be suggested that it is  necessary to add one more pump, Multiflo MFC 385, for the dewatering pit process.

References

ALGIFARI, A., Ibrahim, E., & Abro, A. (2021). PERENCANAAN SISTEM DEWATERING TAMBANG PT. ULIMA NITRA JOBSITE MME DARMO DI PIT ELANG, MUARA ENIM, SUMATERA SELATAN (Doctoral dissertation, Sriwijaya University).

Adnyano, A. I. A., & Bagaskoro, M. (2020). Kajian Teknis Dewatering System Tambang Pada Pertambangan Batubara. Jurnal Promine, 8(1), 28-33.

Asmiani, N., Widodo, S., Sanjaya, B., Nawir, A., Jafar, N., & Thamsi, A. B. (2023, May). The effect of grain size on the compressive strength of canary shell bio-briquette. In AIP Conference Proceedings (Vol. 2595, No. 1). AIP Publishing.

Aswadi, M., Husain, J. R., Gazali, A., & Thamsi, A. B. (2022). Spread Of Laterite Nickel Based on Drill Data at PT Manunggal Sarana Surya Pratama, Southeast Sulawesi Province. Journal of Geology and Exploration, 1(2), 51-57.

Chow, V. T.,1959., Open Channel Hydraulic., McGraw-Hill Book Company., USA

Limantara, L. M., 2010., Hidrologi Praktis., Penerbit Lubuk Agung., Bandung

Muslimah, N., 2012., Kajian Teknis Sistem Penyaliran Tambang Terbuka Batubara Pit A Pada PT. Indomining Kecamatan Sangasanga Kabupaten Kutai Kartanegara Provinsi Kalimantan Timur., Universitas Negeri Padang., Padang

Pipa HDPE Untuk Air Bersih Bertekanan., 2005., Standard SNI., Jakarta

Raflesia, C., 2016., Perencanaan Sistem Penyaliran Di Blok B Rawa Seribu Tambang Batubara PT. Mandala Karya Prima Job Site PT. Mandiri Intiperkasa Kalimantan Utara., Universitas Negeri Padang., Padang.

Sulfahmi, P., Asmiani, N., & Thamsi, A. B. (2020). ANALISIS MANFAAT SEKTOR PERTAMBANGAN TERHADAP PREKONOMIAN KAB LUWU TIMUR MENGGUNAKAN METODE ANALASIS LOCATION QUENTION DAN ANALISIS SHIFT-SHARE. Jurnal GEOSAPTA Vol, 6(2), 81.

Thamsi, A. B. (2017). Estimasi Cadangan Terukur Endapan Nikel Laterit Cog 2, 0% Menggunakan Metode Inverse Distance Pada Pt. Teknik Alum Service, Blok X. J. Geomine.

Zain, M. R., Triantoro, A., & Dwiatmoko, M. U. (2020) OPTIMALISASI SISTEM DEWATERING PT ENERGI BATUBARA LESTARI. Jurnal GEOSAPTA, 5(1). 41-44.

Pane, D. H., Rusli, H. A. R., & Kasim, T. (2018). EVALUASI SISTEM DEWATERING PADA TAMBANG EMAS BAWAH TANAH CIURUG L. 450 BAGIAN SELATAN DI UPBE PONGKOR PT. ANEKA TAMBANG (PERSERO) TBK. Bina Tambang, 3(2), 904-919.

Downloads

Published

2023-01-31

How to Cite

Putri Hamdan, A., Anshariah, A., Bakri, H., & Nullah Yusuf, F. (2023). Perencanaan Kebutuhan Pompa Untuk Sistem Dewatering Tambang Emas Desa Bakan Kabupaten Bolaang Mongondow. Journal of Mining Insight, 1(1), 17–25. https://doi.org/10.58227/jmi.v1i1.40